Is there a way to make the AIA report populate while using a time and material billing rule or a combined time and material/progress billing rule? It works fine for a progress billing or for the progess billing part of a combined rule.

Best answer by ChrisWeidner

@pslaughter , This would be possible by customizing the AIA report. I see the main grouping is “=PMProformaProgressLine.RefNbr” . I assume (not positive), this grouping and other fields are pulling solely from the ProgressLines. You could try to rework the report but know that this may create incorrect values. UPVOTE this product idea which I believe is requesting the same  

 

2 replies

ChrisWeidner
Varsity I
Forum|alt.badge.img
  • Varsity I
  • Answer
  • January 13, 2022

@pslaughter , This would be possible by customizing the AIA report. I see the main grouping is “=PMProformaProgressLine.RefNbr” . I assume (not positive), this grouping and other fields are pulling solely from the ProgressLines. You could try to rework the report but know that this may create incorrect values. UPVOTE this product idea which I believe is requesting the same  

 


joelhoffman
Acumatica Moderator
Forum|alt.badge.img+2
  • Acumatica Moderator
  • January 14, 2022

@pslaughter  @ChrisWeidner - You are correct, the only way to do this currently is via customization.  We do have this on our roadmap, but it has not been assigned a release.  As mentioned earlier, please vote for the idea, as we use that information as part of our roadmap evaluations.  Thanks.