Error: sales order cannot be shipped in full. There are not enough stock items available for the X project

  • July 22, 2023
  • 1 reply
  • 375 views

Forum|alt.badge.img

Hi Acumatica People,

I am setting up a new environment and I did the following: 

-created a customer after I had set-up my customer classes

-set up my reason codes

-set up my warehouse with locations 

-created two items

-Entered receipts (like this): 

-Entered the order: 

We haven’t changed any setting associated with Project (which is part of our planned implementation). This order is non-project order (identified in our settings as X).

 


 

I am presently going through the “Project Inventory Tracking: Implementation Checklist”. Are there standard set-ups for the non-project, X, that I have missed?

 

Thanks,

 

Patrick

 

 

 

 

 

 

Best answer by PatrickBacon

After researching a little more, we have enabled project inventory “tracking by location” and on page 298 of this release document, http://acumatica-builds.s3.amazonaws.com/builds/21.2/ReleaseNotes/AcumaticaERP_2021R2_ReleaseNotes_full.pdf, we need to link the inventory account with an account group. I will have to try this.

1 reply

Forum|alt.badge.img
  • Author
  • Varsity I
  • Answer
  • July 22, 2023

After researching a little more, we have enabled project inventory “tracking by location” and on page 298 of this release document, http://acumatica-builds.s3.amazonaws.com/builds/21.2/ReleaseNotes/AcumaticaERP_2021R2_ReleaseNotes_full.pdf, we need to link the inventory account with an account group. I will have to try this.