Hello all,
How can I calculate the original subcontract amount for an individual subcontract? Or where can I find it?
The Ext Cost column looks to be dynamic but I’m looking to keep a track of the original cost too.
Hello all,
How can I calculate the original subcontract amount for an individual subcontract? Or where can I find it?
The Ext Cost column looks to be dynamic but I’m looking to keep a track of the original cost too.
Best answer by harshitasethia74
Hey
you can find the original subcontract amount either under Projects screen → Cost Budget tab → Original Committed Amount for the respective Project task, Cost code & A/c group that’s in the subcontract.
or
Under the Committments screen → Original Committed Amount for the respective subcontract.
Regards.