We are just getting started with Acumatica so we have a lot to learn -  Is it possible in acumatica to build a routing that contains both sequential and parallel operations ? 

2 replies

Userlevel 7
Badge +3

Scheduling operations to be worked in parallel is a feature we are working to provide in an upcoming release.

 

Do you have any idea when this will be available ?  Do you know of any workaround?  This is a very common practice in manufacturing so I am sure others must have this same issue..