I have customers that are process manufacturers that make materials that cannot be disassembled.  The materials are produced and reported through a Move transaction.  The Move transaction is designed to allow for you to scrap completed items on the Production Order but not to Reject and Rework completed items.

Has anyone else developed a customization or process that they have found to work well for Rejecting a finished good, segregating the materials in a Material Review location, and then either scrapping, reworking, or returning to regular stock?

Best answer by andrestamour43

@JNelson79, have you explored using the scrap action quarantine? This allows users to receive the produced item in question to a holding location for further review. At which point the item might be scrapped, reworked, or transferred to regular stock.  

2 replies

Forum|alt.badge.img+3
  • Acumatica Employee
  • Answer
  • July 15, 2022

@JNelson79, have you explored using the scrap action quarantine? This allows users to receive the produced item in question to a holding location for further review. At which point the item might be scrapped, reworked, or transferred to regular stock.  


  • Author
  • Freshman II
  • July 25, 2022

We went through the quarantine process again and we think that is going to work.  Thank you for the response and advice.