Hi all - I’ve run into a situation I am hoping someone can provide insight / a solution for. We had a production order (RO A) for quantity 4. Welding completed OP ID 10 for quantity 10 (they built 6 over). Assembly processed RO OP ID 20 and 30 for quantity 4 and then RO A was closed.
The cost of the 6 extra welded parts were rolled into that of the 4 completed parts. Is there a way to reopen a production order to complete OP ID 20 and 30 for the remaining 6?
Any advice is appreciated - thanks!