I am a relatively new Acumatica user and have a question. I am wanting to set up “PLanned Start” and “Planned End” dates to match an overall Project schedule. I will then set up a Task that is tied to a Project Task that’s schedule matches the budget for that project task. ex: A cost collector project task is budgeted for 80 hours. I would assign a task to an employee that spans two work weeks in the start and due date fields of the task. So far, all of that works great.
The ISSUE:
On a Task that will take several days/weeks to complete will not allow an employee to submit a time card that includes task work items on a task that is not yet completed. What can be done about that? Is there a setting I need to change?
Thanks!