If Use Fixed Manufacturing Time on Inventory Planning Preferences is not checked, we expect MRP to use manufacturing time from the BOM.
We are having trouble getting it to take Queue Time into account. DA-L0 and DA-L1 both have a queue time of 4 days.
Created an SO for DA-L0 on 3/15. Here is the MRP Result, with the planned action dates for the production orders being 3/15.
Shouldn’t the queue time of 4 days force the action date back 4 days?
If I create the RO from the SO, it does back up the start date.