We are implementing Acumatica. We have about 100 machines grouped into 5 work centers. A typical production order is about 300 pieces and typically runs 2-4 days. The issue we are having it that as we test scheduling it is spreading the work from one production order to all 25 machines in the work center.
It is there a way to keep a single production order confined to a single machine without turning the all 100 machines into individual workcenters?