Journal Entry to a project with cost codes

  • June 11, 2024
  • 2 replies
  • 109 views

Forum|alt.badge.img

Keep getting this message when attempting to post a JE to a project:

The 10-530 cost code is not present in the project budget with the combination of the 1 project task and the UNBILLED account group.

Db JE is going to account 11500

UNBILLED account group account codes:

 

Best answer by nhatnghetinh

 

Hi @jddonnell55 

+ On the Budget Details screen: Cost Code: 10-530 belongs to Account Group "BUDEN"
+ While Account: 11500 belongs to Account Group "UNBILLED"
+Therefore on the Journal Transactions screen: you cannot use Account: 11500 for Cost Code 10-530 of Account Group "BUDEN"

Please see my correct usage example in the screenshot below.

 

 

 

 

Best Regards,

NNT

2 replies

nhatnghetinh
Captain II
Forum|alt.badge.img+11
  • Captain II
  • Answer
  • June 12, 2024

 

Hi @jddonnell55 

+ On the Budget Details screen: Cost Code: 10-530 belongs to Account Group "BUDEN"
+ While Account: 11500 belongs to Account Group "UNBILLED"
+Therefore on the Journal Transactions screen: you cannot use Account: 11500 for Cost Code 10-530 of Account Group "BUDEN"

Please see my correct usage example in the screenshot below.

 

 

 

 

Best Regards,

NNT


Forum|alt.badge.img
  • Author
  • Freshman II
  • June 12, 2024

Thank you.