How does PO approvals work on projects with multiple projects on the lines?

  • 7 April 2022
  • 3 replies
  • 109 views

Userlevel 2

We have a client that does PO’s which contain expense lines for multiple Projects.

If you have PO approvals setup by project who does the PO approval request go to?

 

icon

Best answer by Laura02 7 April 2022, 14:37

View original

3 replies

Badge +16

Hello,

The answer depends on the design of your approval map.

Here is an example of Change Requests being routed to the Approver on the Project’s Defaults tab.

 

 

Here is an example of the AP Bill being routed to the Project Manager:

Notice:  Employee is not set to a specific employee id or to the company tree, but to a field related to the document being approved.  I circled the button we use to expand the list of available fields. 

Laura

Badge +16

Suppose one PO has three projects with three managers.  Depending on how you set up the approval, it could be that any one of the project managers could approve the document, or that All project managers whose projects are on the PO need to approve the PO. Is up to you; the setting I’m referring to is on Rule Actions tab:

 

Userlevel 2

Thanks so much Laura, will try it out and get back to you :) 

Reply


About Acumatica ERP system
Acumatica Cloud ERP provides the best business management solution for transforming your company to thrive in the new digital economy. Built on a future-proof platform with open architecture for rapid integrations, scalability, and ease of use, Acumatica delivers unparalleled value to small and midmarket organizations. Connected Business. Delivered.