I have a commitment created in Procore, synced to Acumatica, and released. Let’s say it’s for $10,000 with 10% retainage or $1,000.
We need to issue a change order and reduce the commitment value to $500. I’m getting an error when trying to release the change order:
“The change order cannot be released because the line total of the Subcontract will go negative.”
I believe the issue is that the retainage is excluded from the line total. So I cannot create a change order that will reduce the amount to less than $1000, which is the same value as the retainage on the original subcontract.
Any ideas on how I can proceed?
Thanks, Colm
Best answer by mike.gillum